Home Up Cost Management
Project Project Life Cycle Process Group Integration Management Scope Management Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management Professional Responsibility

 

 

 

 

Project Cost Management

(Level of difficulty: 4 / 10)

 

Try to understand and memorize the formulas! Not do worry too much about cost calculation and EVM. Understand the concept well, the questions are rather easy.

  

Project Cost Management Processes Process Group
Cost Estimating Planning
Cost Budgeting Planning
Cost Control Monitoring and Controlling

 Cost Estimating

bullet

Estimates the costs of the resources required to complete project activities

bullet

Types of Cost
bullet

Variable Costs

bullet

Fixed Costs

bullet

Direct Costs

bullet

Indirect Costs

Cost Budgeting

bullet

Cost budgeting is the process of assigning a cost to an individual work package. To goal is to establish a cost baseline.

bullet

A Project Cost baseline  show what is expected to be spent on the project.

 

Cost Control

bullet

Influences the factors that cause Cost variances

bullet

Control the changes to the Project Budget

 

 

Formulas:

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

(EV Comes first in the above formulas)

EAC = BAC / CPI  (no variance)

EAC = AC + ETC (assumptions were fundamentally flawed)

EAC = AC + (BAC - EV)   (variances are atypical and similar variances will not occur)

EAC = [AC + (BAC - EV) /CPI ]  (variances are typical and will change)

VAC = BAC - EAC

 
CV = EV -AC
 
CV = +ve
Cost Underrun
CV = -ve
Cost Overrun
CPI = EV / AC
 
CPI > 1
Cost is greater than budgeted
CPI < 1
Cost is less than budgeted

 

SV = EV - PV
 
SV = +ve
Project is on schedule
SV = -ve
Project is behind schedule
SPI = EV / PV
 
SPI > 1
Ahead of schedule
SPI < 1
Behind schedule

 

Accounting Concept
Description
Notes
Present Value (PV)
Future Value (FV)
r = interest rate
n = number of time period
The today value of future cash flow.
 
PV = FV/(1 + r) /n
The higher the  PV, the better
Net Present Value (NPV)
The present value of cash inflow less the present value of cash outflow
Negative NPV is unfavourable;
NPV is higher the better.
Internal Rate of Return (IRR)
The interest rate that makes the NPV of cash flow equal zero.
The higher the IRR, the better.
Payback period
The number of time periods required until cash inflows equal costs.
The lower the payback period, the better.
Benefit Cost Ration (BCR)
A ratio describing the relationship between the cost and benefits of a proposed project.
BCR less than 1 is unfavourable; BCR is higher the better.
Opportunity Cost
The difference in benefit received between a chosen project and a rejected project.
 

Note: NPV is greater the better. IRR is greater the better.

 

 

                                    Please contact me at anthony@anthonyyeong.com
                                   
Your Encouragement is my Motivation !
                                    (Please remember to refresh your browser to get the updated version)

                                    Last modified: 06/08/2007              Website hosted since 1995