Home Up Scope Management
Project Project Life Cycle Process Group Integration Management Scope Management Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management Professional Responsibility

 

 

 

 

Project Scope Management

(Level of difficulty: 7 / 10)

 Scope Management is a process to ensure the project includes only the work required to complete the project. Work excluded are not part of the project.

Project Scope Management Processes Process Group
Scope Planning Planning
Scope Definition Planning
Create WBS Planning
Scope Verification Monitoring and Controlling
Scope Control Monitoring and Controlling

Scope Planning

bullet

create Scope Management Plan

bullet

documents how Project Scope will be defined, verified and controlled

bullet

describe how WBS will be created
 

 

Scope Definition

bullet

develop a detailed Project Scope Statement

bullet

what is and is not included in the project

bullet

Stakeholder Management - the Project Manager must identify and
the stakeholders, determine their needs and expectations, then
manage and influence their expectations to ensure project success

 

Create WBS

bullet

subdivide project deliverables into smaller and more manageable
components (decomposition)

bullet

the lowest level should be a work package that can be assigned to
an individual or business unit

bullet

WBS can be created by Chronological order or Functional units

 

Scope Verification

bullet

verify that the work done satisfies the scope of the project

bullet

must be done at the end of each project phase

bullet

documents  those completed deliverables that have been accepted

bullet       take note this process is not about verifying the project scope but the works  to be
      done against the project plan and project scope management plan.

 

 

Scope Control

bullet

influence the factors that create project scope changes

bullet

control the impact of  the requested changes

bullet

Change Control System

bullet

Most Change Requests are the result of an external event;
a problem in the project and value adding to the business need.

 

Project Success depends primarily on Customer Satisfaction, so manage the Project Scope seriously.

 

 

 

 

 

 

 

 

                                    Please contact me at anthony@anthonyyeong.com
                                   
Your Encouragement is my Motivation !
                                    (Please remember to refresh your browser to get the updated version)

                                    Last modified: 06/07/2007              Website hosted since 1995