Project Time Management

(Level of difficulty: 6 / 10)

This area could be difficult for those who are not familiar with scheduling calculation.
However, just follow the logic and the procedures, it should be fine.

Project Time Management Processes Process Group
Activity Defintion Planning
Activity Sequencing Planning
Activity Resource Estimating Planning
Activity Duration Estimating Planning
Schedule Development Planning
Schedule Control Monitoring and Controlling

Activity Definition

bullet

Identifies the specific schedule activities to deliver project deliverables

bullet

WBS is decomposed into schedule activities

 

Activity Sequencing

bullet

Identifies the dependencies among the schedule activities

bullet

Network Diagrams: PDM or AON

bullet

PERT is not Network Diagram

bullet

Dependencies
bullet

Finish-to-Start

bullet

Start-to-Start

bullet

Finish-to-Finish

bullet

Start-to-Finish

bullet

ADM or AOA
bullet

dummy activity might be required

bullet

Types of Dependencies
bullet

Mandatory

bullet

Discretionary

bullet

External

 

Activity Resource Estimating

bullet

estimates the type and quantity of resources

bullet

resources include equipment and materials as well as people

Activity Duration Estimating

bullet

Identifies the time require to establish each activity

bullet

PERT: duration = (O + 4M +P)/6

Schedule Development

bullet

put all estimates together and produce a project schedule

bullet

schedule is calendar based

bullet

Critical Path is the longest duration path in the project

bullet

CPM: identify the Critical Path

bullet

Fast Tracking: doing critical path activities in parallel

bullet

Crashing: move more resources to complete the critical path activities

bullet

Milestone has zero duration

Schedule Control
 

bullet

Control the changes to project schedule

bullet

Progress Reporting
















                                    Please contact me at anthony@anthonyyeong.com if you have any good suggestions.
                                  
Your Encouragement is my Motivation ! (Please remember to refresh your browser to get the updated version)
Link Disclaimer: This personal website is not responsible for the copyrights, contents or reliability of any linked websites. The listing of a web link shall not be taken as endorsement of the products or services provided by the linked website. This website cannot guarantee that the web links will work all of the time as it has no control over the availability of linked pages. This website has no intention to advertise for any specific linked websites. This personal website provide links to other websites for the convenience of other web users with common interests.  
                                    Last modified: 08/01/2010              Website hosted since 1995